Loughborough University
Leicestershire, UK
LE11 3TU
+44 (0)1509 263171
Loughborough University

Loughborough University Institutional Repository

Please use this identifier to cite or link to this item: https://dspace.lboro.ac.uk/2134/9181

Title: A lean and agile construction system as a set of countermeasures to improve health, safety and productivity in mechanical and electrical construction
Authors: Court, Peter F.
Pasquire, Christine L.
Gibb, Alistair G.F.
Keywords: Construction system
Countermeasures
Last planner
Health and safety
Productivity
Issue Date: 2009
Publisher: © Lean Construction Institute
Citation: COURT, P.F., PASQUIRE, C.L. and GIBB, A.G.F., 2009. A lean and agile construction system as a set of countermeasures to improve health, safety and productivity in mechanical and electrical construction. Lean Construction Journal, pp. 61-76.
Abstract: This paper presents certain aspects of the findings of a research project to develop and implement a Lean and agile mechanical and electrical (M&E) Construction System on a case study project. The objective of the research project for the sponsor company is to improve its projects site operations making them safer for the worker and improving efficiency and productivity by overcoming the problems and issues that it faces in the M&E industry within the UK construction sector. The research finds that using the System on the case study project, and when compared to a traditional method, a 37% reduction in onsite labour was achieved; no time slippage occurred during onsite assembly to delay or disrupt other trades; less workers onsite were exposed to lower health and safety risks from site operations leading to zero reportable accidents; good ergonomics was achieved by focussing on workplace design thus improving workers wellbeing; an improved quality of work was achieved for those required on site carrying out simpler assembly tasks; productivity gains were achieved by eliminating process waste; a 7% direct labour reduction was achieved leading to no labour cost escalation that otherwise could have occurred further reducing the risk of labour cost escalation. Significantly, an overall productivity of 116% was achieved using the Construction System which compares favourably to the Building Services Research and Information Association (BSRIA) findings of an average overall productivity of only 37% when compared to observed best practice for the projects in that case study research. Also, no compression of the commissioning period occurred with the built facility being handed over to the customer on time.
Description: This article was published in the serial, Lean Construction Journal [© Lean Construction Institute]. The definitive version is available at: http://www.leanconstruction.org/lcj/2009/LCJ_08_012.pdf
Version: Accepted for publication
URI: https://dspace.lboro.ac.uk/2134/9181
Publisher Link: http://www.leanconstruction.org/lcj/paper.html
ISSN: 1555-1369
Appears in Collections:Published Articles (Civil and Building Engineering)

Files associated with this item:

File Description SizeFormat
2009 Court LEAN AGILE CONSTRUCTION TO IMPROVE HS LCJ pre-pub version.pdf336.53 kBAdobe PDFView/Open

 

SFX Query

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.